10.08.2022
											Tajikistan: Reconnection to the Central Asian Power System Project
										
Prepared by Project Management Unit for Electro-Energy Sector for OJSHC “BarqiTojik” and the Asian Development Bank
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
									
		
							23.06.2022
											Tajikistan: Power Sector Development Program
										
Prepared by Implementing Agency: State Establishment «Project Management Unit for Electro-Energy Sector» (SE «PMUES») for the Executing Agency Open Stock Holding Company «Barqi Tojik» (BT), and the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
									
		
							14.06.2022
											Tajikistan: Golovnaya 240 MW Hydropower Plant Rehabilitation Project Prepared
										
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
									
		
							01.02.2022
											Tajikistan: Wholesale Metering and Transmission Reinforcement Project
										
This environmental monitoring report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary
in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or
reference to a particular territory or geographic area in this document, the Asian Development Bank
does not intend to make any judgments as to the legal or other status of any territory or area.
									
		
							01.02.2022
											Tajikistan: Golovnaya 240 MW Hydropower Plant Rehabilitation Project
										
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area
									
		
							01.02.2022
											Tajikistan: Reconnection to the Central Asian Power System Project
										
Prepared by Project Management Unit for Electro-Energy Sector for OSHC Barqi Tojik and the
Asian Development Bank
This environmental monitoring report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments to the legal or other status of any
territory or area.
									
		
							30.03.2022
											Specific Procurement Notice Request for Bids
										
Specific Procurement Notice
 
Request for Bids
 
 
 
Employer: OSHC “Barqi Tojik”
 
Project: RURAL ELECTRIFICATION PROJECT
 
Contract title: Plant, Design, Supply, and Installation of Works for the Construction of the 10 kV Medium Voltage Power Lines and Associated LV Networks for Target Settlements in Khatlon Region
 
Country: Republic of Tajikistan
 
Grant No.: D-504 TJ
 
RFB No: BT/C/01
 
Issued on: 30.03.2022
									
		
							14.12.2021
											Tajikistan: Regional Power Transmission Project
										
I. PROJECT DESCRIPTION
 
1. Tajikistan has made great strides in developing its power supply system since its
 
independence in 1991. However, the country’s power sector suffers from incomplete policies
 
and timid sector reforms, multiple structural weaknesses, and insufficiencies in sector core
 
functions (i.e., generation, transmission, and distribution) as well as inefficient consumption
 
by households, businesses, and government consumers.1 This is compounded by a
 
ballooning debt crisis that has become unsustainable. The main contributors to this crisis are
 
underpricing and nonpayment, high power system losses, aged and obsolete metering and
 
billing systems, weakness in financial management, insufficient cash flow, high debt service
 
obligations, large foreign exchange losses on grants and loans, lack of accountability, little
 
transparency, and poor sector governance.
 									
		
							02.09.2021
											Environmental and Social Impact Assessment (ESIA)
										
Environmental and Social Impact Assessment (ESIA)
of the subcomponent 1b - construction of a new 110/10 kV Isfara-1 substation with the associated construction of a 10-0.4 kV distribution network for power supply to the projected settlement
									
		
							06.08.2021
											Resettlement Action Plan
										
Resettlement Action Plan. Section: 66 kV electrode line and 220kV HVAC Transmission Line Route (T/L South segment)
									
		
							15.07.2021
											Request for bids Rural Electrification Project, Component 2: Provision of Electricity Service to Target Settlements in Khatlon Region
										
Plant, Design, Supply, and Installation of Works for the Construction of the 10 kV Medium Voltage Power Lines and Associated LV Networks for Target Settlements in Khatlon Region
 									
		
							30.06.2021
											Resettlement Action Plan Section: 500 HVAC Transmission Line Route (T/L Central segment)
										
Construction 500 KV Transmission Line South, Central and North Parts of Tajikistan
 									
		
							11.05.2021
											Grant 0778-TAJ: Power Sector Development Program (extension of the term until 15.06.2021)
										G2 - Procurement of Advanced Metering infrastructure, Low-Voltage and Medium-Voltage Enhancement for Dushanbe, Buston, Dangara, Panjakent, Konibodom, Isfara and Istaravshan, plus Boundary Meters									
		
							28.04.2021
											Environmental and Social Impact Assessment (ESIA) of the subcomponent 1b - construction of a new 110/10 kV Isfara-1 substation with the associated construction of a 10-0.4 kV distribution network for power supply to the projected settlement
										
CSP Project Development Objective. The Project Development Objective is to increase quality of and access to energy, social and economic infrastructure services, and contribute to the strengthening of local governance capacity in communities in the project area. 
									
		
							19.04.2021
											ADB Grant 0622-TAJ:  Reconnection to the Central Asian Power System Project
										Contract Award Notice									
		
							19.04.2021
											ADB Grant 0622 : Contract Award Notice. Supply and installation of relay protection systems in various substations, and construction of two 500 kv interconnection points in Sugd substation.
										0622-TAJ:  Reconnection to Central Asian Power System, Package 1									
		
							16.04.2021
											Construction 500 KV transmission line South, Central and North parts of Tajikistan
										
Resettlement Action Plan. Section: 500 HVAC Transmission Line Route (T/L South segment). (Draft)
									
		
							19.03.2021
											Grant 0778-TAJ: Power Sector Development Program
										G2 - Procurement of Advanced Metering infrastructure, Low-Voltage and Medium-Voltage Enhancement for Dushanbe, Buston, Dangara, Panjakent, Konibodom, Isfara and Istaravshan, plus Boundary Meters									
		
							01.02.2021
											Notice of contract award BT/CSP/1BC
										
Notice of contract award Supply and Installation for construction of Isfara-1 110/10 kV SS & distribution networks improvements, line & substation project, Subcomponent 1B
									
		
							22.12.2020
											Contract Award. Installation of wholesale meters at 500kV, 220kV, 110kV, and 35kV levels
										The Republic of Tajikistan has received financing from the Asian Development Bank (ADB) toward the cost of the Wholesale Metering and Transmission Reinforcement Project. Part of this financing will be used for payments under the contract named above. Bidding was open to Bidders from eligible source countries of ADB.
									
	