Name of Project: Energy Loss reduction
Project, Tajikistan Project ID: P089244
Bid/Contract Description: Scope of Contract: Procurement of Complete
Substations and Power Transformers
Duration: ----- Contract Signature Date: --------
Hereby OSHPC “Barki Tojik” informs, that based on evaluation criteria PRG considered that none of submitted proposals fully technically or financially comply with the requirements of previously submitted Bidding Document. Therefore based on World Bank no objection PRG decided to conduct a new bid for above mentioned package.
Awarded Bidder | ||
Name & Address* of awarded bidder |
Bid price at bid opening |
Final bid price |
----------------------------------- |
-------------------- |
-------------------- |
Evaluated Bidder(s) | ||
Name of evaluated bidder(s) |
Bid price at bid opening |
Bid price of evaluated bid |
CHINT Electric Co., Ltd |
1,653,778.50 USD |
1,653,778.50 USD |
LLC “Tavono 2011” |
711,698.80 |
711,698.80 Bidder did not indicate the currency of proposal |
LLC “Osie-Kom” |
830,315.30 |
830,315.30 Bidder did not indicate the currency of proposal |
Network Power Company “Salyut Energy” |
1,653,918.00 USD |
1,653,918.00 USD |
LLC “Umedi Jalolien” |
445,180.00 USD |
445,180.00 USD |
LLC “Karmus Bark” |
1,204,992.00 USD |
1,204,992.00 USD |
LLC “Somon bark” |
786,247.00 |
786,247.00 Bidder did not indicate the currency of proposal |
OJSC “Tojikgidroelectromontaj” |
829,605.00 USD |
829,605.00 USD |
Rejected Bidder(s) | ||
Name of rejected bidder(s) |
Bid price at bid opening |
Reason(s) for rejection |
CHINT Electric Co., Ltd |
1,653,778.50 USD |
Proposal higher then the budget. |
LLC “Tavono 2011” |
711,698.80 |
Bidder did not indicate the currency of proposal |
LLC “Osie-Kom” |
830,315.30 |
Bidder did not indicate the currency of proposal |
Network Power Company “Salyut Energy” |
1,653,918.00 USD |
The Bidder did not indicate any experience in implementation of such supplies The amount of proposal is higher then the budget. |
LLC “Umedi Jalolien” |
445,180.00 USD |
the bidder failed to provide a acceptable Certificates of origin and quality, which will confirm the compliance of the offered products to the specified requirements set in the bidding document. The bidder did not furnish documentary evidence to demonstrate that it meets the experience requirements of having at least 2 successfully executed contracts (similar size and complexity) for supply of the similar goods during the last 3 years; |
LLC “Karmus Bark” |
1,204,992.00 USD |
All submitted certificates were in Chinese Language and it was impossible to determine their content. Also bidder did not indicate any experience in implementation of such supplies. The amount of proposal is higher then the budget |
LLC “Somon bark” |
786,247.00 |
Bidder did not indicate the currency of proposal. Specification do not have the signatures and seals. The Bank Guarantee does not comply to the requirements of Bid. |
OJSC “Tojikgidroelectromontaj” |
829,605.00 USD |
The amount of proposal is higher then the budget |
File: Download