Projects
ADB Grant 0376-TAJ: Golovnaya 240 MW HPP Rehabilitation Project
Lot 1: Rehabilitation Works for Generation Units of Golovnaya HPP
Results of International Competitive Bidding for Plant Design, Supply and Install
Procurement Method: ADB Two Stage Bidding Process
i. Names of Bidders submitted First Stage Bid:
· The JV of Alstom Hydro France, Alstom Hydro Switzerland and GES
· Multiple Contractor ANDRITZ HYDRO
· China Gezhouba Group Company Limited
· SINOHYDRO -HYDROCHINA JV
· TBEA & APP
· VANGUARD - NORINCO INTL JOINT VENTURE
·
ii. Names of Bidders whose bids were rejected in the First Stage Bids and reasons for their rejection:
Bidder |
Reason |
TBEA & APP |
Did not meet the minimum experience requirements set for in Chapter 2.4, Section 3, Volume 1 of the Bid Documents |
VANGUARD - NORINCO INTL JOINT VENTURE |
Did not meet the minimum experience requirements set for in Chapter 2.4, Section 3, Volume 1 of the Bid Documents |
iii. Summary of Second Stage Bids:
Item |
The JV of
|
Multiple Contractor Andritz Hydro |
Sinohydro - HydroChina JV |
China Gezhouba Group Company Limited |
Bid Amount in US $ |
Bid Amount in US $ |
Bid Amount in US $ |
Bid Amount inUS $ | |
Final Bid Price (after discount) |
$130,187,556 |
$105,761,576 |
$78,465,300 |
$69,306,628 |
Evaluation Adjustment for Schedule |
-$1,248,460 |
-$26,212,731 |
-$17,679,261 |
$0 |
Evaluation Adjustment for Unit Efficiency |
-$208,000 |
$192,000 |
-$556,000 |
-$556,000 |
Evaluated Price |
$128,731,096 |
$79,740,845 |
$60,230,039 |
$68,750,628 |
On a basis of systematic evaluation in accordance with ADB procurement procedures, Sinohydro – HydroChina JVwas determined as a winning Bidder with bid price in the amount of US$74,385,245 (say seventy four million three hundred and eighty five thousand two hundred and forty five US Dollars) and TJS32,108,393 (say thirty million one hundred and eight thousand three hundred ninety three Tajik Somoni).