31.10.2016

ADB Grant 0376-TAJ: Golovnaya 240 MW HPP Rehabilitation Project

Lot 1: Rehabilitation Works for Generation Units of Golovnaya HPP

Results of International Competitive Bidding for Plant Design, Supply and Install

Procurement Method: ADB Two Stage Bidding Process

i. Names of Bidders submitted First Stage Bid:

· The JV of Alstom Hydro France, Alstom Hydro Switzerland and GES

· Multiple Contractor ANDRITZ HYDRO

· China Gezhouba Group Company Limited

· SINOHYDRO -HYDROCHINA JV

· TBEA & APP

· VANGUARD - NORINCO INTL JOINT VENTURE

·

ii. Names of Bidders whose bids were rejected in the First Stage Bids and reasons for their rejection:

Bidder

Reason

TBEA & APP

Did not meet the minimum experience requirements set for in Chapter 2.4, Section 3, Volume 1 of the Bid Documents

VANGUARD - NORINCO INTL JOINT VENTURE

Did not meet the minimum experience requirements set for in Chapter 2.4, Section 3, Volume 1 of the Bid Documents

iii. Summary of Second Stage Bids:

Item

The JV of
Alstom Hydro France, Alstom Hydro Switzerland and GES

Multiple Contractor Andritz Hydro

Sinohydro - HydroChina JV

China Gezhouba Group Company Limited

Bid Amount in

US $

Bid Amount in US $

Bid Amount in US $

Bid Amount inUS $

Final Bid Price (after discount)

$130,187,556

$105,761,576

$78,465,300

$69,306,628

Evaluation Adjustment for Schedule

-$1,248,460

-$26,212,731

-$17,679,261

$0

Evaluation Adjustment for Unit Efficiency

-$208,000

$192,000

-$556,000

-$556,000

Evaluated Price

$128,731,096

$79,740,845

$60,230,039

$68,750,628



On a basis of systematic evaluation in accordance with ADB procurement procedures, Sinohydro – HydroChina JVwas determined as a winning Bidder with bid price in the amount of US$74,385,245 (say seventy four million three hundred and eighty five thousand two hundred and forty five US Dollars) and TJS32,108,393 (say thirty million one hundred and eight thousand three hundred ninety three Tajik Somoni).