ADB Grant 0376-TAJ: Golovnaya 240 MW HPP Rehabilitation Project
Lot 2: Rehabilitation Works of Switchyards of Golovnaya Hydropower Plant
Results of International Competitive Bidding for Plant Design, Supply and Install
Procurement Method: ADB Single-Stage, Two Envelope Bidding Procedure
i. Names of Bidders submitted a Bid:
· ATEF Group of Companies LLC (i.e. “ATEF”)
· CHINT Electric Co. Ltd (i.e. “CHINT”)
· Genser Genel Muhendislik Taahhut ve Ticaret AS and
Grid Solutions Enerji Endustrisi AS Consortium
· TBEA Co. Ltd (i.e. “TBEA”)
ii. Name of the bidders whose bid were rejected after the technical evaluation:
Bidder |
Reason for rejection |
ATEF Group of Companies LLC (i.e. “ATEF”)
|
Did not meet the minimum experience requirements set forth in Chapter 2.4, Section 3 of the Bidding Documents |
CHINT Electric Co. Ltd (i.e. “CHINT”)
|
Did not meet the minimum experience requirements set forth in Chapter 2.4, Section 3 of the Bidding Documents |
The financial bid evaluation has shown the following results:
Item |
Genser Genel Muhendislik Taahhut ve Ticaret AS and Grid Solutions Enerji Endustrisi AS Consortium
|
TBEA Co. Ltd (i.e. “TBEA”)
|
Bid amount in US$ |
Bid amount in US$ | |
Final Bid Price (after Discount) |
13,729,029.00$
|
17,483,299.00$
|
Evaluation Adjustment |
103,323$ |
126,342.82$ |
|
|
|
Evaluated Price |
13,832,052.00$ |
17,609,641.82$ |
On a basis of systematic evaluation in accordance with ADB procurement procedures, Genser Genel Muhendislik Taahhut ve Ticaret AS and Grid Solutions Enerji Endustrisi AS Consortium was determined as a winning Bidder with the bid price in amount of US$8,100,000.00 (say eight million and one hundred thousand US Dollars) and Euro 5,065,000.00 (say five million and sixty five thousand Euro).